Florida PSC Issues Order Approving Mid-Course Correction Involving Peoples Gas System (10)
TALLAHASSEE, Florida, July 23 (TNSsro) -- The Florida Public Service Commission issued the following order approving mid-course correction (DOCKET NO. 20220003-GU; ORDER NO. PSC-2022-0287-PCO-GU) on July 22, 2022:
* * *
In re: Purchased gas adjustment (PGA) true-up.
The following Commissioners participated in the disposition of this matter:
ANDREW GILES FAY, Chairman
ART GRAHAM
GARY F. CLARK
MIKE LA ROSA
GABRIELLA PASSIDOMO
ORDER APPROVING PEOPLES GAS SYSTEM'S MIDCOURSE CORRECTION
BY more PR
Ind. Utility Regulatory Commission Issues Weekly Hearing Schedule for July 25-29 (10)
INDIANAPOLIS, Indiana, July 23 (TNSsro) -- The Indiana Indiana Utility Regulatory Commission issued the following weekly hearing schedule:
* * *
Monday, July 25, 2022
CAUSE NO.: 45723; ALJ: SCHUSTER; TIME: 1:30 P.M.; COMMISSIONER: KREVDA; ROOM: PNC, Room 222
IN THE MATTER OF THE PETITION BY SUN CHIEF SOLAR FARM, LLC FOR CERTAIN DETERMINATIONS BY THE COMMISSION WITH RESPECT TO ITS JURISDICTION OVER PETITIONER'S ACTIVITIES AS A GENERATOR OF ELECTRIC POWER.
* * *
Tuesday, July 26, 2022
There more PR
N.C. Environmental Quality Dept. Reviewing Updated Volume Estimate in Colonial Pipeline Fuel Release (10)
RALEIGH, North Carolina, July 23 -- The North Carolina Department of Environmental Quality issued the following news release on July 22, 2022:
The North Carolina Department of Environmental Quality (DEQ) is reviewing an updated volume estimate submitted today by Colonial Pipeline Company under the terms of the 2022 Consent Order.
According to the document submitted today, Colonial estimates a volume of two million gallons of fuel released in the Oehler Nature Preserve near Huntersville, makin more PR
N.Y. Public Service Department Issues Letter Involving Abundant Solar Power (10)
ALBANY, New York, July 23 (TNSsre) -- The New York Department of Public Service issued the text of the following letter on July 22, 2022:
* * *
To: Andrew Van Doorn, Abundant Solar Power Inc., 700 West Metro Park, Rochester, NY, 14623, andrew.vandoorn@abundantsolarenergy.com
RE: 2021 Annual Compliance - Abundant Solar Power Inc.
Dear Andrew Van Doorn:
Thank you for your recent submittal pursuant to Section 3F of the New York State DPS's Uniform Business Practices for Distributed Energy Reso more PR
N.Y. Public Service Department Issues Letter Involving N.Y. Solar Farms (10)
ALBANY, New York, July 23 (TNSsre) -- The New York Department of Public Service issued the text of the following letter on July 22, 2022:
* * *
To: Nathaniel Curtis, NY Solar Farms, Inc., 6 Balsam Circle, New Harbor, ME, 04554, nate@northeast.energy
RE: 2021 Annual Compliance - NY Solar Farms, Inc.
Dear Nathaniel Curtis:
Thank you for your recent submittal pursuant to Section 3F of the New York State DPS's Uniform Business Practices for Distributed Energy Resource Suppliers (UBP-DERS). This more PR
N.Y. Public Service Department Issues Letter Involving Sky Solar (10)
ALBANY, New York, July 23 (TNSsre) -- The New York Department of Public Service issued the text of the following letter on July 22, 2022:
* * *
To: Frank Ruffolo, Sky Solar Inc., 1129 Northern Blvd. Suite 204, Manhasset, NY, 11030, frank.ruffolo@skysolarholdings.com
RE: 2021 Annual Compliance - Sky Solar Inc.
Dear Frank Ruffolo:
Thank you for your recent submittal pursuant to Section 3F of the New York State DPS's Uniform Business Practices for Distributed Energy Resource Suppliers (UBP-DER more PR
|